Earned value management (EVM) integrates

admin2022-08-02  35

问题 Earned value management (EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress.A.qualityB.riskC.changeD.cost

选项

答案 D

解析 挣值管理(EVM)将范围基线与 ( ) 基线以及进度基线结合起来,形成绩效基线,帮助项目管理团队评估和衡量项目绩效和进度。A.质量        B.风险        C.变更        D.成本