A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks
选项
A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299709.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theauditingfunctionthatprovidesfeed
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
A()isasoftwarethatprovidesametho
Aprojectmanagerbelievesthatmodifyin
Alinemanagerprovidesyouwiththreee
Aprojectmanagerbelievesthatmodifyin
Theprojectmanagermustmaintainaneff
Projectmanagerbelievesthatmodifying
Alinemanagerprovidesyouwiththreee
随机试题
InternationalWomen’sDay(8March)isanoccasionmarkedbywomen’sgroupsar
TheDemocrats’TradeTroublesLastweekHousespeakerNancy
Everyoneissurprisedthatshehasfallenoutwithherboyfriend.Theunderline
______feltthatsocietyforcedtoomanyrulesonpeopleandkeptthemfromlivin
组织中不利于分权的因素有()。A.组织规模 B.活动的分散性 C.政策的统
水肿的病因不包括:A.风邪侵表 B.情志失调 C.疮毒内犯 D.饮食不节
患者40岁,左下第一磨牙深龋治疗时不慎穿髓,穿髓孔>1mm,该牙处理方法应选择A
人们经常听到“信息”和“控制”这两个字眼,但往往说不清它们的确切含义。实际上,我
某商场历年的营业额数据分别为313万元,325万元,287万元,342万元,31
材料1:2007年上半年,猪肉价格上涨较快。温家宝总理2007年5月26日到陕西
最新回复
(
0
)