问题
A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks
选项
A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299709.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theauditingfunctionthatprovidesfeed
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
A()isasoftwarethatprovidesametho
Aprojectmanagerbelievesthatmodifyin
Alinemanagerprovidesyouwiththreee
Aprojectmanagerbelievesthatmodifyin
Theprojectmanagermustmaintainaneff
Projectmanagerbelievesthatmodifying
Alinemanagerprovidesyouwiththreee
随机试题
Themostimportantthingtodo______thepollutionassoonaspossible.A、arego
[originaltext]M:Hereisyourcoat.W:Thanks.It’sverykindofyoutoinvite
某图书,正文有12印张,若印制8000册,该书正文的理论用纸量为( )。A.6
传动带过松(跳动)或过紧会造成传动带跳动或打滑。
在Windows资源管理器中,若要选择窗口中离散的文件,在缺省设置下,可以先选择
某检测中心根据交通行业标准JT/T391-2009《公路桥梁盆式支座》做盆式支座
下列指标中能够衡量商业银行所有者投入资本所形成权益的获利水平的是()。A.
证券公司在柜台市场开展业务,下列做法符合投资者适当性管理办法相关规定的是( )
某机械制造加工重点县的应急管理部门人员王某,根据(企业职工伤亡事故分类)(GB
患者男性,78岁,因尿潴留需要导尿,现请你作留置导尿术(在医学模拟人上操作)。(
最新回复
(
0
)