A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks
选项
A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2299709.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theauditingfunctionthatprovidesfeed
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
A()isasoftwarethatprovidesametho
Aprojectmanagerbelievesthatmodifyin
Alinemanagerprovidesyouwiththreee
Aprojectmanagerbelievesthatmodifyin
Theprojectmanagermustmaintainaneff
Projectmanagerbelievesthatmodifying
Alinemanagerprovidesyouwiththreee
随机试题
HasNancystoppedsmokingnow?[originaltext]Nancyhascompletelystayedoffcig
[originaltext]In1789theU.S.governmentpassedalawwhichsaidthatthe
FamilyMattersThismonth,Wyomingpassedabillthatwouldgive
Theviewthat"thereisnodirectlinkbetweenlinguisticformandwhatitrefer
Youprobablyhavenoticedthatpeopleexpresssimilarideasindifferentway
标准稠度用水量、凝结时间、安定性是水泥常规性能检测项目,用于评价水泥物理性能的优
根据以下材料,回答题 SometimesIreallydoubtwhe
下列关于证券市场线说法中,不正确的是( )。A.证券市场线为每一个风险资产进行
既能祛风湿,又能退虚热的药物是A.胡黄连 B.黄柏 C.秦艽 D.地骨皮
平值期权的Delta变化的速度在平值附近最大。()
最新回复
(
0
)