A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks
选项
A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2301738.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Toensuretheprojectteamprovidesthe
Projectmanagerbelievesthatmodifying
A( )isasoftwarethatprovidesametho
A()isasoftwarethatprovidesametho
Alinemanagerprovidesyouwiththreee
Aprojectmanagerbelievesthatmodifyin
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
Projectmanagerbelievesthatmodifying
()isthatitprovidesguidanceanddi
随机试题
(1)Doyoueverfeelasthoughyouspendallyourtimeinmeetings?(2)He
Therearepeoplewhoareespeciallyattractedtothenotionof"climbingthe
Underthepresentsystem,stateenterprisesmust______allprofitstothegover
A.氨水的解离常数Kb增大 B.氨水的解离度α增大 C.溶液的pH值增大
软件开发项目规模度量(sizemeasurement)是估算软件项目工作量、编制
一般地说,如果不进行任何治疗,一个人从感染艾滋病病毒到发病、到死亡,要经过下列哪
Thechangeinthatvillagewasmiraculou
石膏具有的功效是A.滋阴润燥 B.除烦止渴 C.祛痰排脓 D.利尿通淋
经济体制改革必须以()为重点,实现产权有效激励、要素自由流动、价格反应灵活
儿童风湿热的相关发病机制是A.链球菌直接损害 B.Ⅲ型变态反应 C.Ⅳ型
最新回复
(
0
)