A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks
选项
A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
答案
B
解析
转载请注明原文地址:https://tihaiku.com/congyezige/2301738.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Toensuretheprojectteamprovidesthe
Projectmanagerbelievesthatmodifying
A( )isasoftwarethatprovidesametho
A()isasoftwarethatprovidesametho
Alinemanagerprovidesyouwiththreee
Aprojectmanagerbelievesthatmodifyin
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
Projectmanagerbelievesthatmodifying
()isthatitprovidesguidanceanddi
随机试题
ANationThat’sLosingItsToolboxThesceneinsidetheHome
Meetingroomsofvarioussizesareneededfor______.[br][originaltext]In
消防泵组电气控制柜应具有过载保护、短路保护、过压保护、欠压保护功能。
下列有机物中,对于可能处在同一平面上的最多原子数目的判断,正确的是( )。
康复医学的主要工作内容包括康复预防、康复功能评定和三个部分()A.康复服务 B
性大寒、专泻肺中水饮及痰火的药物是()A.麻黄 B.葶苈子 C.白果
全站系统配置文件应全站唯一,该文件描述(),由系统集成厂商完成。(A)I
2020年,我国粮食种植面积11677万公顷,比上年增加70万公顷。其中,稻谷种
下列说法不正确的是()。A.为提高出口货物在国际市场上的竞争能力,世界各国一般
固定利率等额本息还款方式的特征有()。A、每月还款额中利息逐渐增加 B、每月还
最新回复
(
0
)