The most crucial time for project risk assessment is ( ).A. when a problem surfacesB. during the planning phaseC. during the close-out phaseD. after the project schedule has been published
选项
A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published
答案
D
解析
进行项目风险评估最关键的时候是:规划阶段
A:问题出现时
B:规划阶段
C:结束阶段
D:项目进度公布后
转载请注明原文地址:https://tihaiku.com/congyezige/2298420.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Inprojectmanagementandsystemsengine
Inaprojectplan,whentheprojectmana
Projectmanagerbelievesthatmodifying
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
Theprojectmanagermustmaintainaneff
随机试题
Potentiallyofferingapowerfulnewtoolagainstterrorism,researchershave
Thismodeloftypewriterisefficient,economicaland(practice)______forcolle
HowlongdidthespeakerstayinHollywoodlastChristmas?Shestayedtherefor_
Thefirsttwostagesinthedevelopmentofcivilizedmanwereprobablythei
[originaltext]W:Yourresumeisperfect.NowIwanttoknowyouropinionabout
各种运输方式内外部的各个方面的构成和联系,就是( )。 A.运输系统
请列举不少于三种教具。
企业债券发行的中介机构主要有()。A:承销商B:发行人C:担保人D:律师
聘任教师的形式有()。 A.招聘B.续聘 C.解聘D.不聘
最新回复
(
0
)