问题 The most crucial time for project risk assessment is (    ).A. when a problem surfacesB. during the planning phaseC. during the close-out phaseD. after the project schedule has been published

选项 A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published

答案 D

解析 进行项目风险评估最关键的时候是:规划阶段

A:问题出现时

B:规划阶段

C:结束阶段

D:项目进度公布后