首页
登录
从业资格
Risk management allows the project manag
Risk management allows the project manag
资格题库
2022-08-02
92
问题
Risk management allows the project manager and the project team not to( ).A.eliminate most risks during the planning phase of the projectB.identify project risksC.identify impacts of various risksD.plan suitable responses
选项
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
答案
A
解析
题干:()不属于风险管理中项目经理和项目团队职责的是
A 排除大部分项目计划中的风险 所以选答案A
B 识别项目风险
C 识别风险的影响
D 制订合理的风险应对
项目团队在风险管理中的管理过程主要有:
1)规划风险管理
2)识别风险
3)实施定性风险分析
4)实施定量风险分析
5)规划风险应对
6)监控风险
转载请注明原文地址:https://tihaiku.com/congyezige/2302026.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
Inaprojectplan,whentheprojectmana
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Riskmanagement's( )istoassureunce
随机试题
—Don’tgotherealoneinsuchlatehours.—Don’tworry.I______.A、do
[audioFiles]2018m6s/audio_ezfj_001_180602[/audioFiles]Children’sAggressiveBeh
Ifthewholeframeworkofthethesishadbeendesignedbeforehand,______(就会节省很多
下列各项中,属于长期借款的特殊性保护条款的是()。A.限制企业资本支出规模
左心室和右心室在解剖上的主要区别是A.右心室是心脏最靠后的部分 B.左心室是心
IFG的诊断标准是()A.≥7.8mmol/L-<11.1mmol/
体育教学模式具有一套稳定的教学活动框架和程序,其核心要素()。A.理论基础
某企业2011年末资产负债表有关项目的金额如下:流动资产总额2000万元,其中现
采用资格预审方法招标的主要缺点是()。A、增加了评标费用B、增加了招标投标流程
如果银行贷款到期不能正常收回或银行与借款人之间发生纠纷,就应该依靠法律手段来强制
最新回复
(
0
)