问题 Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERTB.Resource levellingC.Schedule compressionD.Critical chain methoD.

选项 A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain methoD.

答案 D

解析 PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成。A. PERT B. 资源平衡C. 进度压缩 D. 关键链法