问题
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).A.Cost VarianceB.Schedule VarianceC.Earned ValueD.Cost Performed Index
选项
A.Cost Variance
B.Schedule Variance
C.Earned Value
D.Cost Performed Index
答案
A
解析
成本偏差是实际完成工作对应的预算与实际发生费用之差。
转载请注明原文地址:https://tihaiku.com/congyezige/2413185.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
( )isthebudgetedamountforthework
Theconnectionbetweentwonetworkstof
ThedifferencevaluebetweenBudgetedCo
( )mustbebetweenon-linedeploymenta
随机试题
Runningslowlyfor(some)threemileseveryday(isproved)agood(form)of(ex
ThesentimentalityofTom’sscreenplaywassoextremethatitborderedon______.
Whatwillcitylifebelikeinthefuture?Somepeoplethinkthatlifeinth
A.甲状腺干制剂 B.手术治疗 C.两者皆有 D.两者皆无甲状腺冷结节的处
根据《证券投资基金法》,信息技术系统服务机构未向国务院证券监督管理机构提供相关技
在二次系统上工作前应做好准备,了解(),核对控制保护设备、测控设备主机或
标准作业指变电运维工作应严格执行现场运维标准化作业,细化工作步骤,量化关键工艺,
认识了小数点向右移动一位小数值就扩大10倍,从而想到,如果小数点向左移动一位小数
单独评估建筑物价值的情况有()。A.在房地产投保火灾险时评估其保险价值
旅客携带伴侣犬、猫进境,须持有输出国(或地区)官方兽医检疫机关出具的检疫证书和(
最新回复
(
0
)