The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).A.Cost VarianceB.Schedule VarianceC.Earned ValueD.Cost Performed Index
选项
A.Cost Variance
B.Schedule Variance
C.Earned Value
D.Cost Performed Index
答案
A
解析
成本偏差是实际完成工作对应的预算与实际发生费用之差。
转载请注明原文地址:https://tihaiku.com/congyezige/2413185.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
( )isthebudgetedamountforthework
Theconnectionbetweentwonetworkstof
ThedifferencevaluebetweenBudgetedCo
( )mustbebetweenon-linedeploymenta
随机试题
BritainoccupiedJavaduringtheNapoleonicWars.BoththeBritishandlaterthe
Thefirstmanwhocookedhisfood,insteadofeatingitraw,livedsolonga
[audioFiles]audio_etoefz_037(20051)[/audioFiles]A、Hewenttothelibrarytwice
Whoisthemanspeakingto?[br][originaltext]W:Goodafternoon,Dr.Anderson’
在火灾报警系统中,消防应急广播主界面信息特征,描述不正确的一项是()。A.当主
B
角膜中央的厚度为A.500~540μm B.500~550μm C.500~
A.600 B.800 C.1000 D.1200
某企业批量生产一种零件,投产批量为6件,经过4道工序加工,按照加工顺序,单件每道
下列说法正确的有()。A:旗形保持的时间越长,它保持原有趋势的能力越强B:如在
最新回复
(
0
)