(  ) is the budgeted amount for the work

最全题库2022-08-02  37

问题 (  ) is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。A.Planned valueB.Actual costC.Earned valueD.Cost variance

选项 A.Planned value
B.Actual cost
C.Earned value
D.Cost variance

答案 C

解析 挣值是在一个既定的时间段内实际完所工作分解结构中的计划活动所对应的预算。