In project management, a () is a list of
In project management, a () is a list of
练习题库
2022-08-02
89
问题
In project management, a () is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter
选项
答案
A
解析
在项目管理中,()是项目的里程碑、活动和交付物的列表,通常包括开始和完成日期。这些因素往往用于估计在资源配置、预算和持续时间等方面,并与依赖关系和计划事件有关。A、计划 B、工作分解结构 C、工作说明书D、章程
转载请注明原文地址:https://tihaiku.com/congyezige/2301815.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
Projectmanagerbelievesthatmodifying
数据库管理系统(DatabaseManagementSystem)是一种操纵
TheProjectManagementTriangleisamod
随机试题
ThetwomajornovelistsoftheRomanticperiodareJaneAustenand______.A、Char
Thereisapopularbeliefamongparentsthatschoolsarenolongerintereste
灾区人员如何开展救灾和避灾,对保证灾区人员的自身安全和控制灾情的扩大具有重要的作
A.CFA(定居因子)B.ST(耐热肠毒素)C.SLT(志贺样毒素)D.LT(不
矿业城市表现出的城市形态是()。A.星座型形态 B.放射型形态 C.组团
A. B. C. D.
建筑场所内配置的灭火器应定期进行配置和外观检查,下列检查项目不属于外观检查内容的
(2017年真题)有学者这样解释法的产生:最初的纠纷解决方式可能是双方找到一位共
诊断噪声性听力损伤主要测定( )。A.声强 B.声压 C.听阈 D.痛阑
下列哪一种测量常用来作为计算某病发病率的分母A.观察到的病例数 B.观察到的新
最新回复
(
0
)