In project management, a () is a list of
In project management, a () is a list of
练习题库
2022-08-02
51
问题
In project management, a () is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter
选项
答案
A
解析
在项目管理中,()是项目的里程碑、活动和交付物的列表,通常包括开始和完成日期。这些因素往往用于估计在资源配置、预算和持续时间等方面,并与依赖关系和计划事件有关。A、计划 B、工作分解结构 C、工作说明书D、章程
转载请注明原文地址:https://tihaiku.com/congyezige/2301815.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
Projectmanagerbelievesthatmodifying
数据库管理系统(DatabaseManagementSystem)是一种操纵
TheProjectManagementTriangleisamod
随机试题
[originaltext]M:Congratulations!Ijustheardaboutyouracceptanceintolaws
UniversitiesmustdealbetterwithcomplaintsWithstudentcompl
TheOriginofMoneyIntheearlieststagesofman’sd
Shewastheonlyoneofthefewgirlswho________passedtheexamination.A、wasB、
构建绿色金融组织体系为商业银行开展绿色金融的节奏中的()。A.第一步
下列选项中,不能作为保证人的是( )。A.某公司财务部主任 B.某实验中
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
用人单位额外支付劳动者一个月工资后可以解除劳动合同的情形有( )。A.劳动者不
(2018年真题)县级以上地方各级预算的调整方案应当提请本级人民代表大会常务委员
有地下层的基础工程,可按( )划分检验批。A.变形缝 B.地下层 C.楼层
最新回复
(
0
)