In project management and systems engineering, ( ) is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.A.RBSB.PBSC.GBSD.WBS
选项
A.RBS
B.PBS
C.GBS
D.WBS
答案
D
解析
在项目管理和系统工程中,WBS是将项目分解为更小的组件的可交付成果。这是一个重要的项目交付成果,将团队的工作组织到可管理的部分。
转载请注明原文地址:https://tihaiku.com/congyezige/2301752.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Softwareengineeringisthestudyandan
Inprojectmanagementandsystemsengine
Inaprojectplan,whentheprojectmana
信息物理系统(CPS,Cyber-PhysicalSystems)是一个综合
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
随机试题
CultureShockI.CultureshockPeoplehavedifficultyin(1)_____toanewcultur
[originaltext]W:Whendidyoubecomeinterestedincollectingstamps?M:Oh,wh
板、次梁与主梁交叉处,当有圈梁或垫梁时,主梁的钢筋在下。
人口自然增加数等于当期出生人口减去死亡人口加上净流出人口数。( )
下列总平面布置的原则中不包括的是()。A:满足生产和工艺流程的要求,利于组织生
城市是纯粹的人为产物,大部分由混凝土组成,环境干燥,人来人往,污染严重。很难想象
下列各组脉象中,脉位相反的是( )。A.浮脉与虚脉 B.濡脉与弱脉 C.洪
2021年3月,某县税务机关拟对辖区内某房地产开发企业开发的房地产项目进行
某企业是一家食品机械设备加工企业,有焊接、机加工、装配、调试车间以及锅炉房、配电
国际工程投标报价工作包括①工程现场调查;②组织投标报价班子;③基础单价计算;④标
最新回复
(
0
)