Establishing a project()involves listen

题库2022-08-02  22

问题 Establishing a project()involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan                    B.risk managementC.scope management plan          D.management schedule

选项

答案 D

解析 建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划   B、风险管理计划C、范围管理计划   D、进度管理计划