All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur
选项
A.Determine the a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approveD.by management
D.Manage changes as they occur
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理
转载请注明原文地址:https://tihaiku.com/congyezige/2299754.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
[audioFiles]audio_eufm_j32_001(20082)[/audioFiles]A、Inahotelroom.B、Inares
Globalizationhasspurredonthistrendthroughtheubiquitousinternettoreali
Whatisthemeaningrelationshipbetweenflowerandtulip?A、Polysemy.B、Homonymy
新闻播音的特点是用事实说话和( )。A.以情感人 B.以理服人 C.以新感
电气主接线设计的基本要求是()。A.可靠性 B.灵活性 C.美观性 D.
(2021年真题)商业银行等金融机构设计市场风险限额体系时应综合考虑的因紊包括(
下列哪项是异常恶露A.产后第3天,恶露有血腥味不臭 B.产后第4天,血性恶露中
住宅建筑设计要点中,以下关于套内空间的叙述错误的是()。A.外窗窗台距楼面
东北省某市的一大型商业综合体,该综合体于2017年12月开始建设,2018年6月
A.实际有病,试验阴性 B.实际无病,试验阳性 C.实际有病,试验阳性 D
最新回复
(
0
)