All of followings should be done by the
All of followings should be done by the
免费题库
2022-08-02
77
问题
All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur
选项
A.Determine the a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approveD.by management
D.Manage changes as they occur
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理
转载请注明原文地址:https://tihaiku.com/congyezige/2299754.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
Anthropologistsagreethatourprimitiveancestorswhoinhabitedthetropicspro
德育是教育者培养受教育者品德的活动,它包括__________教育、政治教育、法
大叶性肺炎灰色肝样变期,肺泡内浸润的细胞主要是()。A.嗜酸性粒细胞 B.多
天王补心丹主治证候的病因病机是()A.心脾两虚,气血不足 B.心阴不
李老师上课时,在讲到中国画的工笔人物画时,把各个朝代画家及作品进行了分析、比较,
抢救对硫磷等硫代类有机磷中毒者,洗胃液忌用A.清水 B.高锰酸钾溶液 C.温
患儿男,8个月。羊乳喂养,未加辅食。为预防营养性巨幼红细胞性贫血的发生,最好多食
马斯洛提出的需求层次理论,认为人有五种基本需求,由低级到高级依次构成需要的层次正
2016年,全国城市公园数量排名前五的省份依次是广东、浙江、江苏、山东和云南,公
患者女性,40岁,既往有风湿性心脏病史,近2年来出现劳力性呼吸困难,1天前因受凉
最新回复
(
0
)