All of followings should be done by the
All of followings should be done by the
免费题库
2022-08-02
44
问题
All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur
选项
A.Determine the a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approveD.by management
D.Manage changes as they occur
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理
转载请注明原文地址:https://tihaiku.com/congyezige/2299754.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
[originaltext]M:Shakinganinfantoutofangerorfrustrationcanleadtoseve
下列各句中,加点的成语使用不恰当的一项是()。A. B. C. D.
教师根据学生新的、意外的情况,迅速而正确地做出判断,随机应变地采取及时、恰当而有
我国教育目的是建立在_____基础上。
苯巴比妥连续用药产生耐药性的主要原因是A、被血浆中假性胆碱酶迅速水解破坏 B、
在司法判决前,社会工作者小董为犯罪嫌疑人吴某撰写犯罪嫌疑人调查报告。该报告不包括
甲8周岁,多次在国际钢琴大赛中获奖,并获得大量奖金。甲的父母乙、丙为了甲的利益,
货运量结构反映了在各种运输方式完成的货运量中,()之间的比例关系。A:不同运输
适用于紧急情况或涉及高科技应用产品和服务的采购方式是()。A.单一来源采购
甲公司是一家C国电信运营商。该公司员工入职后需参加入职培训,培训内容有:在为顾客
最新回复
(
0
)