All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur
选项
A.Determine the a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approveD.by management
D.Manage changes as they occur
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理
转载请注明原文地址:https://tihaiku.com/congyezige/2299754.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
UsingLyricstoDevelopStudents’CriticalLiteracySonglyr
Completethetablebelow.WriteNOMORETHANTHREEWORDSAND/ORANUMBERforeac
You______(无论多么小心都不为过)whenyoudriveacar.cannotbetoocareful本题考查对cannot…too…结
Fearisanemotiondevelopedfromlifeexperienceratherthananinbornnatureo
TheArtofFriendshipA)OneeveningafewyearsagoIf
A.上肢处于Ⅰ期时 B.上肢处于Ⅲ期时 C.上肢处于Ⅳ期时 D.上肢处于Ⅴ
患者男性,26岁,因车祸造成面部外伤,耳、鼻出血。检查见面部两侧不对称,右侧下睑
关于直肠癌哪项是错误的A.约占大肠癌的60%左右 B.常见部位为直肠壶腹部
下列不属于运营系统非结构化要素的是()。A.人力资源及组织策略 B.运营系统
为探讨儿童白血病的病因,研究者选择了100例确诊为白血病的儿童,同时选择了100
最新回复
(
0
)