问题
All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approveD.by managementD.Manage changes as they occur
选项
A.Determine the a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approveD.by management
D.Manage changes as they occur
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理
转载请注明原文地址:https://tihaiku.com/congyezige/2299754.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
Volcanicfireandglacialicearenaturalenemies.Eruptionsatglaciatedvo
(1)Noteveryself-drivingcarcompanyisahi-techunicorneagertodisrupt
现场制作的原木结构的含水率不应大于下列哪个数值?()A.25% B.2
A.高渗性非酮症性昏迷 B.呼吸性酸中毒 C.倾倒综合征 D.低磷血症
专业风险管理委员会对管理层负责,协助管理层履行的职责不包括( )。A.指导、协
A.糖皮质激素 B.输新鲜全血 C.丙酸睾酮 D.抗胸腺球蛋白 E.一叶
甲、乙、丙共同绑架案 被告人:甲,男,20岁,无业。被告人:乙,男,15岁,无
男性,30岁,牧民。1周前捕猎旱獭,3天前发现左下肢外侧有一小水泡,并逐渐形成脓
提供劳务交易的履约进度,可以选择的确定方法有()。A.技术人员测量的完工进
目前,固定资产投资统计起点为( )万元。A.50 B.100 C.300
最新回复
(
0
)