( )is the process of implementing risk
( )is the process of implementing risk
admin
2022-08-02
102
问题
( )is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk ,and evaluating risk process effectiveness throughout the project。A.Identify risksB.Control risksC.Plan risk responsesD.Plan risk management
选项
A.Identify risks
B.Control risks
C.Plan risk responses
D.Plan risk management
答案
B
解析
翻译如下 控制风险是执行风险响应计划,追踪已识别的风险,监控剩余风险,识别新风险和评价风险应对效果的一个过程。
转载请注明原文地址:https://tihaiku.com/congyezige/2302999.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
()istheprocessofmonitoringthest
( )isaprocessofdevelopingadocumen
( )isaprocessofmonitoringthestatu
PlanQualityistheprocessofidentifyi
PerformQualityControlistheprocesso
Validatescopeistheprocessofformali
The()processanalyzestheeffectofrisk
Agoalofthe()processistodetermin
Integration()istheprocessofveri
PerformQualityControlistheprocesso
随机试题
Botany,thestudyofplants,occupiesapeculiarpositioninthehistoryof
SpeakerA:Excuseme,doyouneedahand?SpeakerB;______A、Oh,yes,please.I
Wehavenotdecidedwhichhotel______.A、tostayatB、tostayC、stayingatD、for
Itoftenhappensthatanumberofapplicantswithalmostidenticalqualifica
Agreatchangeinagricultureinthe19thcenturyincludedtwothings:thein
NorthPoleExplorationsIfSantaCla
[originaltext]M:Whatwastheprocessthatbroughtyoutothisprogram?W:Iha
[originaltext]Goodmorning,ladiesandgentlemen.Welcomehere.Today,I’d
两个自然数的最小公倍数是351,和是66,这两个数的乘积是多少?()A.
A.ST段呈上斜型下移 B.ST段弓背向上抬高 C.ST段弓背向下抬高 D
最新回复
(
0
)