问题 Project schedule management is made up of six management processes including:activity definition, activity sequencing,(  ) , and schedule control by order.A.activity duration estimating, schedule developing, activity resource estimatingB .activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

选项 A.activity duration estimating, schedule developing, activity resource estimating
B .activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating

答案 B

解析 项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制定进度计划及进度控制六个步骤。
以上六个步骤具有先后顺序,因此选择“活动的资源估算”activityresourceestimating、“活动历时估算”activitydurationestimating、制定进度计划scheduledevelopment,所以选B。