首页
登录
从业资格
Project schedule management is made up o
Project schedule management is made up o
考试题库
2022-08-02
58
问题
Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.A.activity duration estimating, schedule developing, activity resource estimatingB .activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
选项
A.activity duration estimating, schedule developing, activity resource estimating
B .activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
答案
B
解析
项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制定进度计划及进度控制六个步骤。
以上六个步骤具有先后顺序,因此选择“活动的资源估算”activityresourceestimating、“活动历时估算”activitydurationestimating、制定进度计划scheduledevelopment,所以选B。
转载请注明原文地址:https://tihaiku.com/congyezige/2296949.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thehighestlevelofqualitymanagement
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Configurationmanagementisfocusedont
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
TheProjectManagementTriangleisamod
随机试题
Videorecordersandphotocopiers,eventicketmachinesontherailways,ofte
"City-as-School"isspecialbecauseitis______.[br]Whatdotheteachersat"
Designingforsustainability:whatarethechallengesbehindgreenmate
SpotthedifferenceATaxonomichistoryhasbeenma
某事业单位事业支出400万元,其中专项支出55万元,人员支出180万元;经营支出
投资本金20万元,在年复利5.5%情况下,大约需要( )年可使本金达到40万元
下列哪一种不是大肠埃希菌耐热肠毒素的特性A.对热稳定,100℃加热20分钟仍不被
心理治疗的最高目标是A:症状减轻或缓解 B:行为改变 C:态度改变 D:人
下列属于混凝土及抹灰面涂饰方法的有( )A.喷涂 B.滚涂 C.刷涂 D
肝性脑病注射支链氨基酸的主要作用是 A.减少肠道内氨的形成和吸收 B.纠正氨
最新回复
(
0
)