首页
登录
从业资格
Project schedule management is made up o
Project schedule management is made up o
考试题库
2022-08-02
45
问题
Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.A.activity duration estimating, schedule developing, activity resource estimatingB .activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
选项
A.activity duration estimating, schedule developing, activity resource estimating
B .activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
答案
B
解析
项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制定进度计划及进度控制六个步骤。
以上六个步骤具有先后顺序,因此选择“活动的资源估算”activityresourceestimating、“活动历时估算”activitydurationestimating、制定进度计划scheduledevelopment,所以选B。
转载请注明原文地址:https://tihaiku.com/congyezige/2296949.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thehighestlevelofqualitymanagement
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Configurationmanagementisfocusedont
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
TheProjectManagementTriangleisamod
随机试题
Itiseasytobecynicalaboutgovernment—andrarelydoessuchcynicismgou
Abalanceddietprovidesanadequateintakeofnutrientsformaintenanceof
Whenonehasgoodhealth,_____shouldfeelfortunate.(2010)A、youB、theyC、heD、we
HiringaCarOnlineOnlinecarhirepromisestobecheap
Themisunderstandingofawordcouldevenaffectthewayawarended.[br]Fort
Demandissoaringforshortcourses,fromdrummingtoshoe-making,amongpeo
有限责任公司的成立时间为()。A.申请设立登记日期 B.营业执照签发日期
某饭店要招聘厨师、财会人员,如果对应聘者进行测试,应该主要用()进行甄选。
将重组DNA导入宿主细胞所用的方法中不包括A.感染 B.转化 C.转染 D
下列关于资金申请报告编制要求的说法中,错误的是()。A.项目单位应对咨询机构编制
最新回复
(
0
)