A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.A.EssencesB.ElementsC.PurposesD.Issues
选项
A.Essences
B.Elements
C.Purposes
D.Issues
答案
B
解析
时间表(计划表)在项目规划和项目组合管理中使用广泛。 时间表上的(元素)可能与工作分解结构(WBS)的终端元素,工作说明书,或合同数据需求清单等密切相关。
A.精华
B.元素
C.用途
D.问题
转载请注明原文地址:http://tihaiku.com/congyezige/2302923.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
随机试题
Amongthemanywaysinwhichpeoplecommunicatethroughspeech,publicspeak
InconsideringhowtheAmericanfamilyischanging,thestartingpointisth
Researchintoself-awarenessconsistentlyshowsthatmostpeoplethinkandsp
InBritain,thetopspectatorsportisfootball.Thissportwasseriously
Amajorreasonforconflictintheanimalworldisterritory.Themaleanima
[img]2021m3x/ct_ve01004002m_eyyjsbreadc_0380_202103[/img]Informationte
PartⅡReadingComprehension(SkimmingandScanning)Directions:Inthispart,y
A.血液系统症状 B.神经系统症状 C.肝肾损伤 D.胃肠道症状 E.脑
下列因子中,不参与原核生物翻译过程的是 A.IFB.EF1C.EFT D.
位于县城的一月饼生产企业为一般纳税人,2020年7月转让一处仓库,取得含税收入4
最新回复
(
0
)