问题
A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.A.EssencesB.ElementsC.PurposesD.Issues
选项
A.Essences
B.Elements
C.Purposes
D.Issues
答案
B
解析
时间表(计划表)在项目规划和项目组合管理中使用广泛。 时间表上的(元素)可能与工作分解结构(WBS)的终端元素,工作说明书,或合同数据需求清单等密切相关。
A.精华
B.元素
C.用途
D.问题
转载请注明原文地址:http://tihaiku.com/congyezige/2302923.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Establishingaproject( )involveslis
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
随机试题
Feelfreeto______theengineerformoreassistance.A、callonB、calltoC、callfo
SPEAK:DRAWL::A、eat:sipB、run:canterC、lament:sighD、gain:coverE、look:
[originaltext]W:Thisfoodisterrible.Ican’tevenfinishmydinner.M:Ikno
TheCaseforKillingMyMotherA)Mymotherwantedtodie,but
FISH:SCALES::A、limb:skinB、foot:toeC、vertebrate:backboneD、insect:exos
Parentingwasneverapieceofcakeinanyage,butprobablythegreatestso
下列关于烧结普通砖的说法正确的有( )。A.烧结普通砖不具有保温隔热性能 B
患者,男性,23岁。抗结核治疗6个月,现发现有盗汗、咳嗽、咳痰,追问病史,患者认
患者,男性,37岁,劳累受凉后,水肿、尿少(约每天400ml)5天。查:血压15
躯体运动中枢位于大脑皮质的()。A.额叶 B.颞叶 C.枕叶 D.顶叶
最新回复
(
0
)