问题
Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule
选项
A.cost management plan
B.risk management plan
C.scope management plan
D.management schedule
答案
D
解析
建立一个项目(进度管理计划)包含列出里程碑、活动和可交付的计划起止日期,其中要考虑到员工的安排的因素。
A.成本管理计划
B.风险管理计划
C.范围管理计划
D.进度管理计划
转载请注明原文地址:http://tihaiku.com/congyezige/2302550.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
Whyyoushouldn’ttrytobeamorningpersonA)We’veallhear
Congestedcitiesarefastbecomingtesttubesforscientistsstudyingthei
Billisanexampleofaseverelydisabledpersonwhohasbecome______atmanys
Afriendofmineonceaskedmeaquestion:"Whosaidlifewasgoingtobefa
Hungryprehistorichunters,notclimatechange,droveelephantstoextinctio
下面需要进行根管预备的是A.根管治疗术 B.干髓术 C.活髓切断术 D.直
下列关于电子式储蓄国债特点的描述,正确的有( )。A.方便国债投资者,提高了国债
必须按照国务院卫生行政部门的有关规定,严格执行消毒隔离制度,防止发生内感染和医源
直流电源系统对负载供电,应按()设置分电屏。距离远近$;$负载电流$
某工厂进行接触粉尘与尘肺关系的队列研究得知,该工厂工人尘肺年死亡率为0.48‰,
最新回复
(
0
)