In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ( )are not output of activity definition.A.Activity listB.Work Breakdown StructuresC.Activity AttributesD.Milestone Lists
选项
A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists
答案
B
解析
项目时间管理中, 定义活动是识别和记录为完成项目可交付成果而需采取的具体行动的过程,以下()不是定义活动的输出。A.活动清单B.工作分解结构C.活动属性D.里程碑清单定义活动包括:活动清单、活动属性、里程碑清单。故B选项不是 进度管理过程
转载请注明原文地址:http://tihaiku.com/congyezige/2303628.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Qualitymanagementensuresthatanorgan
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
( )managementincludesnegotiatingthe
Projectmanagerbelievesthatmodifying
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
随机试题
孩子的性格受家庭环境影响很大。Thecharactersofchildrenaregreatlyinfluencedbyhomeenviro
HowInterpretersWork?I.UnderstandingA.Aboutwordsa
Inanefforttoexplainhowmostoflanguage,whichisnotsodirectlyrela
SurvivalSkillsforaJobYouDetestA)Weallhaveheard
Backgroundmusichurtsorhindersworkplaceefficiency.A、正确B、错误B文章里说,由于老板们在听音乐
Thereisatimewhenjobseekerssimplywrotelettersofapplication."Just
描述精神活性物质的使用、陶醉、滥用以及依赖的差异。
联合试运转费以定额建筑安装工程费为基数,按( )的费率计算。A.0.03%
血清总蛋白的参考值为()A.2~4g/LB.4~6g/LC.60~80g/LD
治疗胸痹,祛邪治标时可用( )。A.通阳散寒 B.理气化痰 C.活血化瘀
最新回复
(
0
)