In project time management, activity def
In project time management, activity def
练习题库
2022-08-02
99
问题
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ( )are not output of activity definition.A.Activity listB.Work Breakdown StructuresC.Activity AttributesD.Milestone Lists
选项
A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists
答案
B
解析
项目时间管理中, 定义活动是识别和记录为完成项目可交付成果而需采取的具体行动的过程,以下()不是定义活动的输出。A.活动清单B.工作分解结构C.活动属性D.里程碑清单定义活动包括:活动清单、活动属性、里程碑清单。故B选项不是 进度管理过程
转载请注明原文地址:http://tihaiku.com/congyezige/2303628.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Qualitymanagementensuresthatanorgan
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
( )managementincludesnegotiatingthe
Projectmanagerbelievesthatmodifying
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
随机试题
[originaltext]M:It’sonlyaboutonekilometerleft.Lei’sspeedup.W:Oh,I’d
加强职业道德建设,要把职业道德建设同建立和完善职业道德监督机制结合起来,并和相应
麻黄碱药理特点包括()A.促使储存的去甲肾上腺素释放 B.对其气管平滑肌的
二期梅毒的临床表现是:()A.梅毒疹 B.树胶样肿 C.硬下疳 D.
脑膜瘤的血管造影诊断特征是()A.颈外动脉供血 B.肿瘤血管栏栅状 C.血管
房屋新开工面积包括上期跨入报告期继续施工的房屋面积。()
某植物在停止供水和恢复供水条件下,气孔开度(即气孔开放程度)与光合速率的变化如图
( )是先提出问题并设定问题的若干个答案,由被调查者对设定的答案进行选择。A.
中国证券业协会自收到完整的承销备案材料的()个工作日内未提出异议的,则视为承销备
主动脉听诊区闻及收缩期喷射样杂音,向颈部传导,最可能的诊断是 A.二
最新回复
(
0
)