首页
登录
从业资格
The inputs of developing project managem
The inputs of developing project managem
最全题库
2022-08-02
93
问题
The inputs of developing project management plan do not include ( ).A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes
选项
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
答案
B
解析
制定项目管理计划的输入不包括:
A. 项目章程
B. 干系人管理
C. 项目范围说明书
D. 其他子计划过程输出
不包括项目干系人管理,答案为B
转载请注明原文地址:http://tihaiku.com/congyezige/2301964.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Configurationmanagementisfocusedont
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
( )isaprocessofdevelopingadetail
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
随机试题
Nowastothematteroflying.Youwanttobeverycarefulaboutlying;other
AfamousUSclimatescientistatthecentreofthe"climategate’hasbeen
Complainingaboutfaultygoodsorbadservicearenevereasy.【M1】
Auctions(拍卖)arepublicsalesofgoods,conductedbyanofficiallyapproved
[originaltext]BrightonisapopularseasidetownonthesouthcoastofEngl
考题
已知某运输企业进行仓库装卸货物定额的统计分析,对5个工人完成100件产品装卸的工
患者,女,28岁。被人发现昏迷且休克,屋内有火炉,查体:体温36℃,BP:80/
2003年1月22日,公安部发布了加强公安机关内部管理的“五条禁令”。禁令规定,
职业卫生统计调查最常用的调查方法是() A.普査B.典型调查 C.抽样
最新回复
(
0
)