The Perform Integrated Change Control
The Perform Integrated Change Control
考试题库
2022-08-02
43
问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。
转载请注明原文地址:http://tihaiku.com/congyezige/2299717.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isameasureofscheduleperformance
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
PerformQualityControlistheprocesso
hePerformIntegratedChangeControlpro
( )seekstoperformrootcauseinvestig
Youhavejusttakencontrolofaproject
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
Manyoftheactivitiesperformedduring
随机试题
Shouldthegovernmentencouragesomebusinessestomovefromcitiestorural
[originaltext]W:Comein!M:Hi,ProfessorJane!Doyouhaveaminute?W:Fredr
刺绣(embroidery)是中国艺术里一枚璀璨的珍珠。从君王所穿的华丽的龙袍(dragonrobe)到当今时尚界的流行刺绣。刺绣给我们的生活和文化增加了如此
速度单位“米每秒”用计量单位符号表示,下列中错误的是()。A.米.秒-1
统计生产的第一个阶段是确定()。A.统计调查内容 B.统计需求 C.统计指标
胎儿宫内窘迫时,孕妇一般采取的卧位是A.仰卧位 B.左侧卧位 C.右侧卧位
有限责任公司以下情形中应当召开临时股东会的有( )A.董事会提议 B.1/3
彩灯连接线路应采用绝缘铜导线,导线截面面积应满足载流量要求,且不应小于()mm
存款人与商业银行在存入款项时不约定存期,但支取时需提前通知约定支取存款日期和金额
男,56岁。心房颤动患者,突然发生命名困难。2周来共发生过5次,每次持续2~15
最新回复
(
0
)