You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.A、Resource assignment matrix B、Change control planC、Project charter D、Client organization chart
选项
A、Resource assignment matrix
B、Change control plan
C、Project charter
D、Client organization chart
答案
B
解析
在项目执行的过程中你刚刚获得项目的控制权利,并且需要了解谁具有范围修正的权限,什么文件提供了该信息。
A.资源分配矩阵
B.变更控制计划
C.项目章程
D.客户的组织结构图
转载请注明原文地址:http://tihaiku.com/congyezige/2297223.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
Establishingaproject( )involveslis
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
随机试题
Ourcompanywillprovideyouwithfreetransportationasyourequestedandcharg
采用分批零件法的企业一般具有的特点是()。A.企业的生产不再按客户的订单组织
下列关于混凝土早强剂的叙述正确的是()。A.硫酸钠早强剂会降低混凝土的抗侵蚀
引起鼻源性球后视神经炎最常见的是()A.以上都不是 B.筛窦炎
在景点示意图前,地陪应向旅游者讲清的问题有( )。A.景点的游览线路 B.景
A.3个月 B.6个月 C.8个月 D.9个月 E.12个月小儿会独坐的
共用题干 YouNeedCourage!ShortlyafterIb
慢性肝炎的病程一般超过A.2周 B.1个月 C.2个月 D.4个月 E.
施工招标中,对投标申请人资格预审可采用的方法是( )。A.合格制和淘汰制 B.
注浆是矿山和岩土工程常用的技术,它的作用包括( )。A.治水防渗 B.对构筑
最新回复
(
0
)