Project work packages are typicallydecomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, andmonitoring and controlling the project work.A.reviewing B.estimating C.auditing D.expecting
选项
A.reviewing
B.estimating
C.auditing
D.expecting
答案
B
解析
转载请注明原文地址:http://tihaiku.com/congyezige/2295956.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
Hotelsandrestaurantsarean______partofthecity;withoutthemthecity’st
Morethantenpercentofmotorwaydeathsarecausedbydriversfallingsleep
Honestyisavirtue,andtellingalieismorallywrong.Buthowcanyou【C1】
InAmerica,peoplearefacedwithmoreandmoredecisionseveryday,whether
如果教师喜欢某些学生,对他们抱有较高期望,经过一段时间,学生感受到教师的关怀、爱
计算不上人屋面均布活荷载时,应按以下( )方法选取计算荷载。A.应同时考虑屋面
某投资项目全投资的净现金流量如下表: 若该项目初始投资中借款比例为50%,
下列哪项是专家系统的特征?A.使用电子邮件发送和批准采购请求。 B.订单一发出
英国英镑汇率采用的标价方法是()。A.美元标价法 B.双向报价法 C.直接
(2018年真题)根据《建设工程安全生产管理条例》,属于施工单位安全责任的有(
最新回复
(
0
)