问题 APMwantedtoshowmanagement, visually, how quality controls were affecting processes.The best tool to accomplish this is(  ) .A.DiagramsB.HistogramsC.FlowchartsD.Control charts

选项 A.Diagrams
B.Histograms
C.Flowcharts
D.Control charts

答案 D

解析 项目经理要想更直观地表示出质量控制是如何影响项目进度的,最好的工具是控制图。