问题 Many useful tools techniques are used in developing schedule.()s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method

选项 A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain method

答案 B

解析 许多有用的工具技术被用于开发进度表。()是一种进度网络分析技术,它修改项目进度以考虑有限的资源
A、PERT B、资源均衡C、进度压缩D、系统交付的进度