问题 ( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.A.Schedule forecastsB.Schedule compressionC.Change requestsD.Data analysis

选项 A.Schedule forecasts
B.Schedule compression
C.Change requests
D.Data analysis

答案 B

解析 翻译:( )技术用于通过快速跟踪或崩溃剩余工作的计划来找到使落后的项目活动与计划保持一致的方法。A、进度预测 B、进度压缩 C、变更请求 D、数据分析