问题 The work breakdown structure (WBS) has been widely used in management for software development project.(  ) is generally NOT vaildated through the WBS.A.schedule and costB.organization structuringC.management coordinationD.quality of work

选项 A.schedule and cost
B.organization structuring
C.management coordination
D.quality of work

答案 D

解析 工作分解结构(WBS)已被广泛用于在管理软件开发项目。( 工作质量)一般不通过WBS 确认。
A.进度和成本 B.组织结构
C.管理协调 D.工作质量

关于WBS的作用有原文如下:

The work breakdown structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable incrementsfrom which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established.The work breakdown structure can be displayed in two forms one in form of a table with subdivision of tasks twoin form of an organisational chart.