( )the process of determining,document
( )the process of determining,document
免费题库
2022-08-02
60
问题
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.A.Plan Scope ManagementB.Collection RequirementsC.Validate ScopeD.Control Scope
选项
A.Plan Scope Management
B.Collection Requirements
C.Validate Scope
D.Control Scope
答案
B
解析
(收集需求)确定、记录和管理利益相关者需求和要求以满足项目目标的过程。
A.规划范围管理
B.收集需求
C.确认范围
D.控制范围
转载请注明原文地址:https://tihaiku.com/congyezige/2298491.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()istheprocessofmonitoringthest
()includestheprocessforincorporat
( )isaprocessofmonitoringthestatu
Managingriskanddocumentingthemisve
PlanQualityistheprocessofidentifyi
()istheprocessofidentifyingindivi
Integration()istheprocessofverify
The()processanalyzestheeffectofrisk
Managingriskanddocumentingthemisve
Agoalofthe()processistodetermin
随机试题
Theworldwideconsumptionofbakeryproductsisincreasing.Manypopulation
[originaltext]PsychologistsinBritainhavesaidthatthelastfullweekof
MSProject主要功能包括( )。A.管理人员不能对项目的最终控制权保持
患者,女,56岁,慢性萎缩性胃炎20余年。胃镜检查:胃窦部大弯侧可见直径约1cm
按照定员标准的综合程度,企业定员标准可分为( )。A.比例定员标准 B.
"缩略”是赶路人与时间搏斗的一种方式。也许,赶路人自有不得不缩略的苦衷,其中也许
下列不属于人身保险的是( )。A.责任保险 B.人寿保险 C.意外伤害保险
对该求助者的初步诊断最可能是( )。A.精神病性障碍 B.严重心理问题 C
在理解重要性概念时,下列表述中错误的是()。A.重要性取决于在具体环境下对错报
(2019年真题)根据《房屋建筑与装饰工程工程量计算规范》(GB50854-20
最新回复
(
0
)