首页
登录
从业资格
Managing risk and documenting them is ve
Managing risk and documenting them is ve
考试题库
2022-08-02
35
问题
Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( ).A.project management planB.project baselineC.risk response planD.risk baseline
选项
A.project management plan
B.project baseline
C.risk response plan
D.risk baseline
答案
A
解析
风险管理和记录他们是非常重要的项目规划过程。你的过程中确定主要风险,包括限制和假设,并计划和应急反应。这些细节将列入项目管理计划中。 A选项:项目管理计划;B选项:项目基准;C选项:风险应对计划;D选项:风险基准。
转载请注明原文地址:https://tihaiku.com/congyezige/2302523.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
( )istheprocessofmanagingprocureme
()istheprocessofdocumenting,analy
()istheprocessofdocumenting.Anal
随机试题
促进经济全球化进程加快的原因主要有()A.科技进步及其在生产中的应用
某公司承接了城市道路信息系统建设项目,由于施工日期正好是7月份的雨季,项目团队为
肺泡A、是球形小囊泡,以肺泡孔开口于肺泡囊 B、表面覆盖着单层扁平上皮 C、
如下结构的药物是 A:硝苯地平 B:尼莫地平 C:氯贝丁酯 D:非诺贝特
大型热电厂一般都有十几回输电线路和几条大口径供热干管引出,特别是供热干管所占的用
根据现行国家标准《自动喷水灭火系统设计规范》(GB50084-2017),关于自
(2016年真题)空军飞行员李海,2014年在执行试飞任务中牺牲,被评定为烈士,
监理规划可能随着工程进展进行不断的补充、修改和完善,这体现了监理规划编写时应满足
施工企业使用强制检定的计量器具,应向指定的计量检定机构申请()。A.后续检
关于胸腰椎Chance骨折叙述错误的是( )。A.为椎体水平状撕裂性损伤 B
最新回复
(
0
)