Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( ).A.project management planB.project baselineC.risk response planD.risk baseline
选项
A.project management plan
B.project baseline
C.risk response plan
D.risk baseline
答案
A
解析
风险管理和记录他们是非常重要的项目规划过程。你的过程中确定主要风险,包括限制和假设,并计划和应急反应。这些细节将列入项目管理计划中。 A选项:项目管理计划;B选项:项目基准;C选项:风险应对计划;D选项:风险基准。
转载请注明原文地址:https://tihaiku.com/congyezige/2302523.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
( )istheprocessofmanagingprocureme
()istheprocessofdocumenting,analy
()istheprocessofdocumenting.Anal
随机试题
Readthesesentencesbelowandthetransferagencyontheoppositepage.Which
Howcanasinglepostagestampbeworth$16800?Anymistakeintheprintin
Thesimpleactofsurrenderingatelephonenumbertoastoreclerkmaynots
WhatWilltheWorldBelikeinFiftyYears?A)Thisweeksome
下列属于物理层的设备有()。A.交换机 B.路由器 C.中继器 D.集线器
不列属于变压器结构参数的是()。
下列内容中,属于结构面积的是( )。A.梁所占面积 B.墙体所占面积 C.
融资前分析和融资后分析的关系,下列说法中正确的是: A.融资前分析是考虑债务融
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
能消肿疗疮的药是A.葛根 B.牛蒡子 C.桑叶 D.柴胡 E.蝉蜕
最新回复
(
0
)