In project network diagram,the number of critical path is().A、noneB、only oneC、only twoD、one or more
选项
A、none
B、only one
C、only two
D、one or more
答案
D
解析
在项目网络图中,关键路径的数量可以有(一条或更多)。A没有B仅有一条B仅有两条D一条或更多。
转载请注明原文地址:https://tihaiku.com/congyezige/2298012.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isaparadigmforenablingnetworka
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
Inaprojectplan,whentheprojectmana
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
随机试题
WhichofthefollowingstatementsisCORRECT?[originaltext]Anarsonattack
Inmanycountries,authorityisseldomquestioned,eitherbecauseitishigh
[originaltext]W:I’mreallygettingworriedaboutMary.Shewilltaketwoexams
ShoppersonBlackFriday,thetraditionalstartoftheholidayshoppingseas
下列何者为现代建筑的雏形?()A.彼得·贝伦斯设计的德国通用电气公司透平车间
下列各句子中,加点的成语使用正确的一句是()。A. B. C. D.
阅读下面材料,回答问题。 小班赵老师发现幼儿进餐时存在各种问题:有的幼儿情绪不
在商业银行支付结算业务中,托收属于( )。A.政府信用 B.商业信用
1972年5月,芝加哥商业交易所(CME)推出()交易。A.股指期货 B.利
已知工作A的紧后工作是B和C,B工作的最迟开始时间为第14天,最早开始时间为第1
最新回复
(
0
)