题库2022-08-02  12

问题 In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has (  ) potential communication channels.A.10B.45C.50D.100

选项 A.10
B.45
C.50
D.100

答案 B

解析 在沟通需求分析过程中,项目经理应该使用潜在沟通渠道或路径的数量,来反映项目沟通的复杂程度。依据梅特卡夫定律,一个有着10个项目干系人的项目拥有____条潜在的沟通渠道。

潜在沟通渠道的总量计算公式为n(n-1)/2,其中,n代表干系人的数量。有10个干系人的项目,就有10(10-1)/2=45条潜在沟通渠道。