Changes may be requested by any stakehol

admin2022-08-02  48

问题 Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT manager B.project manger C.change control board D.project sponsor

选项 A.executive IT manager
B.project manger
C.change control board
D.project sponsor

答案 C

解析 项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。(73)        A.执行经理                B.项目经理                C.变更控制委员会        D.项目发起人
转载请注明原文地址:https://tihaiku.com/congyezige/2295962.html

最新回复(0)