( )assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope and quality.A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan
选项
A. Quantitative Risk Analysis
B. Qualitative Risk Analysis
C. Enterprise Environmental Factors
D. Risk Management Plan
答案
B
解析
定性风险分析利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。
选项A是定量风险分析,选项B是定性风险分析,选项C是企业环境因素,选项D是风险管理计划。故B是正确的。
转载请注明原文地址:https://tihaiku.com/congyezige/2296862.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()assessesthepriorityofidentified
()Assessesthepriorityofidentified
随机试题
Asbestos(石棉)istilegenericnameforanumberofnaturallyoccurringfibrou
Agoodtranslatorisbydefinitionbilingual.Theoppositeisnot【C1】______
PartyRandomThoughtsLastnight,press
C
某国在某年的经济状况分别为:国际收支的经常项目逆差350亿美元,资本项目顺差28
脊髓损伤四肢瘫,患者最常见的死亡原因为A.呼吸道感染 B.高钙血症 C.泌尿
根据相关规定,需要申请施工许可证的工程类型是( )。 A、工程投资额为60万
根据下表回答问题 下列哪种经济体在2008年的进口增长率最低?()A.
呆账核销意味着银行放弃债权。()
关于违约责任,下列表述正确的是()。A.非违约方如果未尽到减损义务,对扩大的损失
最新回复
(
0
)