问题
( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Enterprise Environmental Factors D.Risk Management Plan
选项
A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
答案
B
解析
翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划
转载请注明原文地址:https://tihaiku.com/congyezige/2295935.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()assessesthepriorityofidentified
()Assessesthepriorityofidentified
随机试题
Forthispart,youareallowed30minutestowriteashortessayentitledWhatS
[originaltext]W:Goodevening.WelcometoourTVshowLifeintheFuture.Today
PPP即公私合作模式,是指为减轻政府财政负担,在公共服务领域,政府采取竞争性方式
垂直距离通常是指()A.牙列缺失后、以托恢复后的鼻底到颏底的距离
我国最早的一批近现代大学包括()。A.太学 B.书院 C.京师大学堂
Thechangeinthatvillagewasmiraculou
评定学生学业成绩的方法有很多,其中学生学业成绩评价的基本方法是()。
男性,53岁,在睡眠中突发剧咳而憋醒不能平卧,呼吸急促喘息,咳出粉红色泡沫样痰。
根据《关于加强规划环境影响评价与建设项目环境影响评价联动工作的意见》,下列说法中
沉陷缝填充材料的安装方法可分为()。A.先装法 B.后装法 C.内装法
最新回复
(
0
)