( ) is a type of bar chart that illustra
( ) is a type of bar chart that illustra
考试题库
2022-08-02
6
问题
( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chart B.project histogram C.milestone chart D.project flowchart
选项
A.gantt chart
B.project histogram
C.milestone chart
D.project flowchart
答案
A
解析
甘特图是一类描述项目进度的图表。它说明了一个项目的开始和结束时间。A.甘特图 B.项目直方图C.里程碑图 D.项目流程图
转载请注明原文地址:https://tihaiku.com/congyezige/2295955.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
A()isatypeofbarchartthatillustrat
()isatypeofbarchartthatillustra
随机试题
July15,1994DearMrs.Smith,Thankyouforyourbusiness.Youarecurrently
[originaltext]Drivingaloneinacarincreasesglobaltemperaturesinthel
StatesExperimentwithOut-of-ClassroomLearning[A]Attheendo
[originaltext]W:Hi,Sam,IhatetobotheryoubutIwonderifIcouldhaveaw
治外感热病热入营血之高热神昏谵语,以及火热内生之血热妄行诸证应使用的药物为A.清
Theweatherisaconstantsubjectofcon
关于劳务派遣中的劳动争议,下列描述错误的是()。A.被派遣劳动者与劳务派遣机构
女性,20岁。因乏力、面色苍白、月经增多1个月入院。查体:贫血貌,巩膜无黄染,心
某公司正在论证新建一条生产线项目的可行性。经测算,项目的经济寿命为5年,项目固定
下列不属于桥式起重机主要参数的是()。A.额定起重量 B.跨度 C
最新回复
(
0
)