( )is primarily concerned with defining
( )is primarily concerned with defining
免费题库
2022-08-02
31
问题
( )is primarily concerned with defining and concerning what is and is not included in the project.A.Project Time ManagementB.Project Cost ManagementC.Project Scope ManagementD.Project Communications Management
选项
A.Project Time Management
B.Project Cost Management
C.Project Scope Management
D.Project Communications Management
答案
C
解析
项目范围管理定义并关心哪些工作是项目应该做的哪些不是项目应该做的。
转载请注明原文地址:http://tihaiku.com/congyezige/2302086.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
()isnotprimarilyusedtoprotectth
( )isprimarilyconcernedwithdefining
()isprimarilyconcernedwithdefining
the()isprimarilyconcernedwithacce
Projectsuccessdependsprimarilyon()。
()isprimarilyconcernedwithdefining
The()isprimarilyconcernedwithacc
the()isprimarilyconcernedwithac
()isprimarilyconcernedwithdefining
随机试题
Youwillhearanotherfiveshortrecordings.Eachspeakeristalkingaboutthee
Thenewsitemismainlyabout______.[br][originaltext](21)Recentdiscover
Howaretornadoesdistinguishedfromwhirlwinds?[br]Accordingtothepassage,
Oneofthemostinterestingofallstudiesisthestudyofwordsandwordor
在何情况下可利用图层和图层之间的裁切组关系创建特殊效果:
若流通于银行体系之外的现金为500亿元,商业银行吸收的活期存款为6000亿元,其
患者孙某,11岁,白血病,欲行骨髓移植。下列有关对该患者的护理措施错误的是 A
银行要保持一种产品的竞争优势只能是通过该产品的附加价值来保持,银行在制作市场定位
根据《建设项目环境保护管理条例》及《建设项目竣工环境保护验收管理办法》,关于环境
某施工单位承接了农村公路的5×16m简支板桥施工项目,桥梁上部结构为先张法预应力
最新回复
(
0
)