the ( ) is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables.A.verify scope B.define scope C.quality assurance D.validate scope
选项
A.verify scope
B.define scope
C.quality assurance
D.validate scope
答案
A
解析
翻译:验证范围主要涉及的是交付验收。而质量控制主要关注的是项目可交付成果的正确性和满足规定的质量要求交付。A.验证范围 B.定义范围 C.质量保证 D.确认范围
转载请注明原文地址:http://tihaiku.com/congyezige/2295972.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()isnotprimarilyusedtoprotectth
( )isprimarilyconcernedwithdefining
()isprimarilyconcernedwithdefining
the()isprimarilyconcernedwithacce
Projectsuccessdependsprimarilyon()。
()isprimarilyconcernedwithdefining
The()isprimarilyconcernedwithacc
the()isprimarilyconcernedwithac
()isprimarilyconcernedwithdefining
随机试题
[originaltext]Americacontinuestoleadtheworldasadestinationforinte
ThefloodofwomenintothejobmarketboostedeconomicgrowthandchangedU
AdvertisingEffectTheimportantfactortoconsiderThe【L31】________thatcu
下列哪些费用属于建筑安装工程措施费?()A.工程排污费、工程定额测定费、社会
某电力生产企业2013年末资产负债表主要科目情况如下: 从其资产负债表分析
劳动合同的特点。
筛选简历的方法。
现代人力资源管理从( )看,与传统的人事管理不同,它更强调管理的动态性和组织的
发电厂、变电所中,下列电压互感器形式的选择条件,哪一条是不正确的?()A.35
明挖扩大基础施工,其基础的定位放样工作是根据(),推算出基础边线的定位点。A.
最新回复
(
0
)