All of followings should be done by the
All of followings should be done by the
题库
2022-08-02
79
问题
All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approved by managementD.Manage changes as they occur
选项
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。 A)确定变更已经发生 B)确保变更已达成共识 C)确保所有变更都获得管理层批准 D)在变更发生时,对变更进行管理
转载请注明原文地址:http://tihaiku.com/congyezige/2301727.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
Ihaveheardbothteachersandstudents______wellofhim.A、tospeakB、spokenC
Whatisthemainideaofthefirstparagraph?[br]Whatisthemostimportantch
Itisanage-old【B1】______:MenarefromMars;WomenarefromVenus.Males
TheGoldenGateBridgeopenedtovehicletrafficonMay28,1937.Ithadthe
下列关于国别风险的表述,正确的是( )。A.在风险管理实践中,国别风险管理属于
泌尿、男性疾病肝经湿热证的,临床特点是A.肾子上或阴茎上慢性结节,皮色不变,亦不
通常不导致血浆阴离子间隙(AG)增加的情况是()A.乳酸性酸中毒B.糖尿病性酮
患者女.29岁。患慢性宫颈炎,行物理治疗后禁止性交和盆浴的时间是A.1周 B.
简述义务教育阶段的培养目标。
在患者中心疗法中,设身处地地理解和分享患者内心世界的感情是指A.无条件积极尊重
最新回复
(
0
)