首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
练习题库
2022-08-02
75
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .A.he project is ahead of its planned scheduleB.less work was completed than was planned tC.the cost overrun for work completedD.the cost underrun of performance to date
选项
A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
答案
B
解析
转载请注明原文地址:http://tihaiku.com/congyezige/2299763.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ascheduleiscommonlyusedinprojectp
Theearnedvaluetechniqueisacommonly
Ethernetisthecommonlyusedlocalarea
Ethernetisthecommonlyusedlocalarea
()isaprojectmanagementtechniquefor
Aprojectmanagementtechniquethatisc
Theearnedvaluetechniqueisacommonly
Earnedvaluemanagement(EvM)integrates
Ethernetisthecommonlyusedlocalarea
随机试题
Itisnotunusualforchiefexecutivestocollectmillionsofdollarsayear
ParkandBurgess’smodelhascometobeknownasthe"concentric-zonemodel"
Inordertoutilizefemaletalentseffectively,itmay_________benecessary,a
Youmightthinkalittleglobalwarmingisgoodforfarming.Longer,warmer
设该两种有机物分别为A和B,A的蒸气密度是1.34g/L,B的蒸气密度是2.68g/L,则 答:
睾丸及附睾的急性化脓性感染,中医称为A.子痰 B.囊痈 C.卵子瘟 D.脱
和衷共济∶和合共生A.如临深渊∶如履薄冰 B.或为玉碎∶或为瓦全 C.不入虎
某女,35岁。素患肝火上炎,口苦尿黄,急躁。近日又见目赤肿痛、目生翳膜,宜选用的
仲裁裁决结案的案卷,保存期不少于()年。A.1 B.5 C.8 D.10
(2017年真题)在渗流作用下,非黏性土土体内的颗粒群同时发生移动的现象称为(
最新回复
(
0
)