Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider ( ).A、crashing the ScheduleB、performing resource levelingC、conducting reverse resource allocation SchedulingD、utilizing the critical chair resources
选项
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources
答案
A
解析
由于团队成员之间的冲突,造成项目落后于进度计划,为了解决冲突以使得项目如期完成,你应该考虑:
A.重新安排时间表
B.实行资源调配
C.执行逆向资源分配调度
D.利用关键的主要资源
转载请注明原文地址:http://tihaiku.com/congyezige/2297222.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inaprojectplan,whentheprojectmana
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
WhichofthefollowingProjectScopeMan
随机试题
过去的一年,对中国人民来说是很不寻常的一年,是改革开放和社会主义现代化建设取得显著成就的一年。经济快速发展。国内生产总值比上年增长9.1%,达到11.6
Thatexperienceinfluencessubsequentbehaviorisevidenceofanobviousbu
PassageThree[br]Whatdoestheauthoraimtoindicatebycitingthetwone
财政部门按当地救助对象人数每人每年不低于()元标准筹集城市医疗救助资金,并按分
某软件项目的活动图如下图所示,其中顶点表示项目里程碑,连接顶点的边表示包含的活动
开挖并铺设表土计量的工程内容不包括( )。A.种植草皮 B.填前场地清理
收益法计算中,建筑物剩余经济寿命早于土地使用权剩余期限结束时,房地产价值等于以建
根据《专利法》,授予实用新型专利的条件包括()。A、富有美感B、新颖性C、创
从所给的四个选项中,选择最符合左侧图形规律的一项:
【背景资料】 某机电安装公司,通过竞标承担了某化工厂的设备、管道安装工程。该工
最新回复
(
0
)