首页
登录
从业资格
Estimating activity durations uses info
Estimating activity durations uses info
题库
2022-08-02
61
问题
Estimating activitydurations uses information on activity scope of ( ) , required resource types, estimatedresource quantities, and resource calendars.A.milestone B. baseline C.quality D. work
选项
A.milestone
B. baseline
C.quality
D. work
答案
D
解析
转载请注明原文地址:http://tihaiku.com/congyezige/2295970.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
()isatechniqueforestimatingthedu
EstimateActivityDurationsistheproce
estimatingisatechniqueforestimating
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
TheboardmembersofEONIncorporatedwill______reviewthecredentialsoftheto
Didyoueverhavean【D1】______oranideathatyouknewwasimportant,butyo
[originaltext]M:When’sTomcoming?I’mafraidwearelateforthemeeting.W:
IntheUnitedStates,theneedtoprotectplantandanimalspecieshasbecom
[originaltext]AmyJohnsonwasaveryambitiousandenergeticperson.Shestu
【B1】[br]【B14】A、expensiveB、fasterC、furtherD、cheaperD词义辨析题。空格后是逗号,然后是safer,由
集中供暖系统循环水泵的轴功率,与下列因素的关系,哪些是正确的?()A.与流量
经纪人可以从经纪合同中规定的经纪业务的委托方处获得佣金,关于佣金的说法错误的是(
如图2所示。该建筑是由()设计的。 A.约翰·伍重 B.贝聿铭 C.梁
2016年末,A自治区城镇人口为1542.1万人,城镇化率(城镇人口占总人口比重
最新回复
(
0
)