首页
登录
职称英语
Wolfe Constructions 121 Fifteent
Wolfe Constructions 121 Fifteent
游客
2025-06-17
18
管理
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects. [br] Which of the following project had NOT been finished according to the report?
选项
A、Framing on the 14# townhouse
B、The foundation for the whole complex
C、The electrical and plumbing work
D、Framing on the gym
答案
C
解析
转载请注明原文地址:https://tihaiku.com/zcyy/4122555.html
相关试题推荐
WolfeConstructions121Fifteent
WolfeConstructions121Fifteent
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
随机试题
Whendiditbegintorain?[br][originaltext]W:John,WasitMiningWhenyouWent
Thepartoftheenvironmentalmovementthatdrawsmyfirm’sattentionisthe
试验水池和排水泵房剖面见图示。试验结束后用水泵将池内海水抽往海中,并将水抽至水池
下列关于观察技巧的叙述,不正确的是A.在对方讲话时把视线转移到其他地方 B.要
下列关于药师调剂处方时必须做到的“四查十对”中,“四查”的内容不包括的是A、查处
我国基本比例尺地形图中,1∶10000地形图的图幅经纬差是( )。A.经差30
患者,女性,31岁。行胆总管切开取石、T管引流术,目前为术后第10天,T管引流
住宅专项维修资金管理实行()的原则。A:专户存储 B:专款专用 C:所有权人
有关非竞争性抑制作用,正确的是A.不改变酶促反应的最大速度 B.改变表观Km值
对于符合贷款条件的客户,如其资金周转存在一定的周期性,在准确把握其还款能力的基础
最新回复
(
0
)