To: Robert Williams, School of ArchitectureFrom: James. JohnsonSubject: Air-co

游客2024-06-26  15

问题 To: Robert Williams, School of Architecture
From: James. Johnson
Subject: Air-conditioning Installation Costs for East Hall
Date: June 4, 2006
    I am writing to inform you of the costs of installing air-conditioning for the seven offices and two studio classrooms in East Hall.
Office and Classroom Installation
    Estimates were obtained from three contractors on the costs of covering the offices and classrooms. All these three were in the $20,000 to $25,000 range. The work would take about three weeks.
    Because the central unit would be installed on the roof, some noise problems might occur during a four-or five-day period. And this work could be started from this weekend, and the overtime labor costs of about $1,500 have been included in the estimates.
Additional Installation
    Because a larger installation, including a more powerful central unit, would be necessary to handle the halls and stairways, an additional $6,000 would be required for the equipment. If this additional work were delayed until a later time, a new central unit would be required along with changes in the pipe way.
Subject:【B1】______Costs for East Hall
Office and Classroom Installation:
1. Covering area: seven offices and two【B2】______
2. Possible problem: some【B3】______might occur during a four- or five-day period
Additional Installation:
1. Budget: $6,000
2. A more powerful【B4】______is needed to handle the halls and stairways
3. Additional installation postponement will result in changes in【B5】______ [br] 【B5】

选项

答案 50.the pipe way

解析
转载请注明原文地址:https://tihaiku.com/zcyy/3651506.html
最新回复(0)