首页
登录
职称英语
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
游客
2024-03-11
18
管理
问题
Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、Tourism industry in Berlin suffers.
B、All kinds of equipment gets rusted.
C、Huge maintenance costs accumulate.
D、Complaints by local residents increase.
答案
C
解析
细节推断题。讲座中提到,更糟糕的是,未启用的机场会产生巨额的费用,每个月的费用高达九百万欧元到一千万欧元。由此推知,这些巨额费用是用在维护上的。
转载请注明原文地址:https://tihaiku.com/zcyy/3525667.html
相关试题推荐
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
随机试题
[originaltext]Notlongagoitwasassumedthatthedangersmanwouldmeeti
ItissaidthatGeorgeWashingtonwasoneofthefirsttorealizehowimporta
安装在机械排烟系统管道上的阀为。A.防火阀 B.排烟防火阀 C.排烟
下列哪项关于病例对照研究的论述是正确的A.来自医疗机构的病例代表性强 B.采用
板式橡胶支座的每一加载循环自1.0MPa开始,将压应力以0.03~0.04
艾滋病患者需要进行抗病毒治疗的时间为多长?( )A.1~2年 B.2~10年
操作票印章包括:(____)。已执行$;$未执行$;$作废$;$合格$;$不合格
2011年T市各类社会保险中,参保人数最多的比参保人数最少的多:() A.
对于渗透系数大、地下水丰富的软土地基,人工降低地下水位宜采用()。A.管井
基因表达产物是A.DNA B.RNA C.蛋白质 D.大部分是蛋白质,某些
最新回复
(
0
)