Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、Tourism industry in Berlin suffers.
B、All kinds of equipment gets rusted.
C、Huge maintenance costs accumulate.
D、Complaints by local residents increase.
答案
C
解析
细节推断题。讲座中提到,更糟糕的是,未启用的机场会产生巨额的费用,每个月的费用高达九百万欧元到一千万欧元。由此推知,这些巨额费用是用在维护上的。
转载请注明原文地址:https://tihaiku.com/zcyy/3525667.html
相关试题推荐
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
随机试题
【S1】[br]【S9】J该空格前为情态动词can,空格后为名同damage,因此空格处应选及物动词原形。原句意为“让更多的阳光进入瞳孔,可以______
朴素的plain
______bothsidesaccepttheagreement_______alastingpeacebeestablishedin
China'srecentpolicywillbringthehig
莫泊桑的成名作是()A.《羊脂球》 B.《漂亮朋友》 C.《梅塘之夜》
从“阿拉伯之春”到“冰桶挑战”,互联网在许多事件中都是活动人士和组织者的有效工具
眶下孔的位置在A.眶下缘下2cm处 B.鼻翼外侧1~1.5cm处 C.口角上
某施工单程承接了一DWDM设备安装工程,包括3 个OTM设备安装测试、8个OA
某护士在给乙型肝炎病毒(HBV)携带者注射时,不慎被患者血液污染的针头刺伤手指。
质量控制点的设置应选择施工过程中的重点部位,重点工序和()A.重点流程
最新回复
(
0
)