首页
登录
职称英语
Complete the summary below. Use NO MORE THAN THREE WORDS for each answer
Complete the summary below. Use NO MORE THAN THREE WORDS for each answer
游客
2024-01-07
26
管理
问题
Complete the summary below.
Use NO MORE THAN THREE WORDS for each answer.
PROJECT MANAGENT
Last week’s definition of project management:
Project Management has
a clear【31】
goals, budget and【32】
A project can be divided into【33】
The subject of today’s lecture【34】 [br]
LECTURER:
I’d like to begin today with a quick review of last week’s lecture. We saw the definition of project management as something which has a clear beginning and a clear completion date with goals, a budget and a schedule. We saw its presence in the private and public sectors in many different industries. You’ll also remember that we outlined the life cycle as it were, of a project and looked at the first of a four-stage cycle-establishing the limits of the project.
Today, we’re going to talk broadly about the second stage of project management-developing a plan for the project. Next week we’ll focus on the implementation of the project and then, the final stage-its evaluation.
Let’s get started on today’s topic, though-planning the project. The success of a project will depend on the skills and care which you put in at this initial planning stage. Planning is not only necessary in terms of budget or cost, it’s also crucial that you consider the time-frame of a project and the standards which you’ll be expected to provide. These three elements are, of course, integrated. Project-planning is best conducted as a team - you might have to take responsibility for handing over the final plan but without a team behind you, you’ll find it almost impossible to plan effectively.
We’ll discuss budgetary planning firstly because that is, of course, what you are most likely to be evaluated on by your own manager. Before drawing up a budget, you’ll need to understand the time-frame involved to carry out the work and the standard of delivery at which the labour and materials are to be supplied. Now, this is arguably the most difficult to plan for. You’ll never plan completely accurately for a project in terms of money but you will become better at planning realistically. And it is this part of the planning process that you will do last.
The best way to plan the cost of a project is to consider all the factors involved and how those factors relate to time and standard of delivery. Write these down on a spreadsheet format and begin the task of costing and estimating. The company that you’re employed by will always have their own systems in place for doing this. They will also indicate the kind of profit they are looking for-usually in percentage terms.
The second stage of planning is the allocation of time to a project and for this, you’ll have to canvass others for help. Only by asking the advice and opinions of those with expertise in the field, will you be able to establish the size of each unit of work to be completed and the order in which those units of work should be carried out. Remember that some units of work may be done simultaneously but many cannot. In your tutorials this week, you’ll be introduced to the Gant Chart-that’s G-A-N-T. This method of planning project activities has been very successful in the field of project management. The complete set of tasks involved in a project are identified and then planned in relation to each other. You’ll soon discover that organizing and prioritizing activities is quite an art-form.
The third part of your planning as I said, will affect your money and time considerations and that is the standard of delivery that the project demands. These standards will be outlined in the tender documents if they’ve been your guide or the masterplan from which you’re working. Always make sure that you’ve got ALL of the project-related documents that are available. For every unit of work that is to be completed, you’ll have to write specifications-they are detailed descriptions outlining specific standards of quality in materials and labour. If these specifications are not carefully written and then complied with, the project is unlikely to be successful. These specifications will be referred to many times once the project is underway.
You will also have to deal with a Quality Assurance Manager at this stage who will advise you on the standards which need to be met. Quality management has become a valued component in successful project management companies.
I’ve provided you with an outline of the planning process for project management but you’ll be looking at these three elements in more depth in your tutorials this week.
选项
答案
a schedule
解析
转载请注明原文地址:https://tihaiku.com/zcyy/3341252.html
相关试题推荐
Governmentofficialsauthorized______becausetheywanttohaveacompleteenumer
Whilenotcompletelynonplussedbytheusuallycausticresponsesfrommembersof
ElizabethBishop’sCompletePoems(1927-1979)hascometoseemtomostofits
ElizabethBishop’sCompletePoems(1927-1979)hascometoseemtomostofits
Somepeoplesaythatcensorshipshouldbecancelledcompletely.Doyoua
Questions28-29Completethenotes,whichshowhowtheapproachestodefining’t
Questions28-29Completethenotes,whichshowhowtheapproachestodefining’t
Questions28-29Completethenotes,whichshowhowtheapproachestodefining’t
Questions28-29Completethenotes,whichshowhowtheapproachestodefining’t
Questions28-29Completethenotes,whichshowhowtheapproachestodefining’t
随机试题
EventhoughAfricangamepreserveshavesavedmanyanimals,thereare______tha
TheLostArtofListeningA)"Whywon’theevenlistentomyidea?""Why
全程肉眼血尿提示血尿源自A.膀胱颈部 B.后尿道 C.肾小球 D.膀胱三角
公司合并或分立的,应通知债权人。债权人自接到通知书之日起( )日内,未接到通知书
有……风险,护理诊断陈述方式是PE。
工程造价等于不含税工程造价加上()。A、增值税 B、营业税 C、城市维护建设
《变电验收管理规定》:省检修公司变电运维班履行以下职责()(A)参加厂内验收、
以下不属于社会工作结案时服务对象的正面反应的是()。A.欣喜 B.感激 C
(2016年真题)龚某因生产不符合安全标准的食品罪被一审法院判处有期徒刑5年,并
信度系数在解释个人分数意义时的作用是()。A:估计误差分数的范围B:估计真实分
最新回复
(
0
)