首页
登录
职称英语
If the building project ______ (打算月底前完成的) is delayed, the construction company w
If the building project ______ (打算月底前完成的) is delayed, the construction company w
游客
2023-09-06
22
管理
问题
If the building project ______ (打算月底前完成的) is delayed, the construction company will be fined.
选项
答案
to be completed by the end of this month
解析
题干语法结构完整,因此所填部分应当是能够修饰project的非谓语动词短语;“打算完成的”即“将要完成、还没完成的”,可用to be completed表达;“月底前”可用by the end of this month表达。所译部分还可用定语从句which is to be completed by the end of this month表达。
转载请注明原文地址:https://tihaiku.com/zcyy/2989938.html
相关试题推荐
[originaltext]M:Hithere.(19)Haveyouheardthatthecompanyiscuttingstaff?
[originaltext]M:Hithere.(19)Haveyouheardthatthecompanyiscuttingstaff?
Itisimpossibletogiveanaccurate______ofcompanysales10yearsfromnow.A
Duringtheconstructionofskyscrapers,cranesareusedto______buildingmater
Theenvironmentiseverythingthatsurroundsus;plants,animals,buildings,cou
Hespendsabout10dayseachmonthbackinHongKong,______projectsinthewor
Anexpensiveprojectlikethisis______withthegovernment’saimofreducingpu
Thearchitectdida______ofhowthebuildingwilllookwhenit’sfinished.A、d
Accordingtooneemployee,whowishestoremain______,thecompanyengagedin
A________areacontainsmainlyapartmentbuildingsratherthanofficesorshops.
随机试题
孙权,字(courtesyname)仲谋,今浙江富阳人。15岁时就开始征战沙场。他是一位善于纳贤的英杰,勇敢果断,选拔官员的标准是唯贤任能。他大胆任用了一批
张先生,43岁,汉族中层干部,身高168cm,体重75kg,血压144/89mm
载荷试验中每一级的荷载增量一般取预估试验土层极限荷载的()。A.1/8~1
下列五输穴中,属于本经子穴的是A、大都 B、中渚 C、行间 D、解溪 E
项目信息管理的目的旨在通过有效的项目信息传输的组织和控制为()服务。A、实现项目
执业药师注册的有效期为()。A.1年B.2年C.3年D.4年E.5年
从人口的年龄结构分析,出现负增长的有几个年龄段? A.1个 B.2个
由于某市路边的报刊亭大多属于违章建筑,影响城市形象,而且普遍存在超范围经营等问题
各种运输方式内外部的各个方面的构成和联系,就是( )。 A.运输系统
自主就业的退役士兵入伍前是国家机关工作人员,退出现役后可以选择()。A.与
最新回复
(
0
)