Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、It is the worst managed airport in German history.
B、It is now the biggest and busiest airport in Europe.
C、It has become something of a joke among Germans.
D、It has become a typical symbol of German efficiency.
答案
C
解析
细节辨认题。讲座中提到,由于长期的延期、接连不断的管理问题以及不断飙升的费用,这座机场已经成了德国的一个笑话,也是让当地的政治家、商界领袖以及居民都感到挫败不已的一个问题。
转载请注明原文地址:https://tihaiku.com/zcyy/2909414.html
相关试题推荐
[originaltext]Manypeopledislikewalkingintothebank,standinginlongl
[originaltext]Manypeopledislikewalkingintothebank,standinginlongl
[originaltext]Yuppiesareyoungpeoplewhoearnalotofmoneyandlivein
[originaltext]Yuppiesareyoungpeoplewhoearnalotofmoneyandlivein
[originaltext]Yuppiesareyoungpeoplewhoearnalotofmoneyandlivein
[originaltext]M:Timetoeat!W:Coming.Oh,I’mstarving.Ohyuck!What’sthat
[originaltext]W:We’veallheardthesaying"Laughteristhebestmedicine"How
[originaltext]W:We’veallheardthesaying"Laughteristhebestmedicine"How
[originaltext]Asaresultofrisinguniversitycosts,manystudentsarefin
[originaltext]Asaresultofrisinguniversitycosts,manystudentsarefin
随机试题
Incomparisonwiththelivesofotherpostgraduatestudents,thelifeofas
某企业“生产成本”账户的期初余额为80万元,本期为生产产品发生直接材料费用640
女性,25岁。左膝外上方逐渐隆起包块伴酸痛半年。X线平片:左股骨下端外侧有一病灶
白睛属肺,称为A、风轮 B、肉轮 C、气轮 D、水轮 E、血轮
淋病双球菌对下列具有抵抗力的是A.潮湿 B.高温 C.肥皂 D.消毒剂
330kV及以上设备首次检出乙炔时应立即退出运行。
如图所示,桁架结构中只作用悬挂重块的重力W,此桁架中杆件内力为零的杆数为: A
下列属于工作分析调查阶段的主要工作的有()。A.执行工作分析计划 B.组建工
下列关于“整体观念”的内容叙述不正确的是A.人自身是一个统一的整体 B.人与自
为预防钢筋混凝土结构构造裂缝,大体积混凝土应优选( )等低水化热水泥。A.矿渣水
最新回复
(
0
)