首页
登录
职称英语
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
游客
2023-08-08
40
管理
问题
Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、The municipal government kept changing hands.
B、The construction firm breached the contract.
C、Shortage of funding delayed its construction.
D、Problems of different kinds kept popping up.
答案
D
解析
目的原因题。讲座中提到,2012年,检查员发现消防安全系统不合格,之后又发现有90多米的电缆装错了,4,000扇门的序号不对,自动扶梯太短,登记柜台的数量也不够。由此可知,机场不断延期投入使用是因为层出不穷的问题。
转载请注明原文地址:https://tihaiku.com/zcyy/2909406.html
相关试题推荐
[originaltext]Objectsthatarevibratingmakesounds.Rhythmicsoundvibrations
[originaltext]Inorderforachemicaltobeconsideredadrug,itmusthavethe
[originaltext]Hi,everybody.AsIsaidinmyStateoftheUnionaddress,weliv
[originaltext]Hi,everybody.AsIsaidinmyStateoftheUnionaddress,weliv
[originaltext]IntheUnitedStates,manypeopleoncelivedinlarge,two-and-th
[originaltext]IntheUnitedStates,manypeopleoncelivedinlarge,two-and-th
[originaltext]Easterisamixofthreetraditions:Pagan,HebrewandChristian.
[originaltext]Easterisamixofthreetraditions:Pagan,HebrewandChristian.
[originaltext]Easterisamixofthreetraditions:Pagan,HebrewandChristian.
[originaltext]W:2millionhighschoolseniorsaregearingupthisfalltoappl
随机试题
[originaltext]W:Goodafternoon,Mr.White.YouareinmyAmericanHistory201
Itisnaturalforyoungpeopletobecriticaloftheirparentsattimesand
下列各项中,不属于企业制度基本内容的是( )。A.企业产权制度 B.企业组织
下列各项中,年金净流量的计算公式正确的有()。A.年金净流量=净现值/年金现值系
【说明】小赵被任命为某软件开发项目的专职质量管理人员,他此前只有过三个月的软件开
28岁初产妇,孕39周,规律宫缩8小时入院,LOA位,胎心率136次/分,宫缩3
治疗外阴炎时,使用1:5000高锰酸钾溶液坐浴的主要作用是( )。A.杀菌
紧缩性的财政政策措施包括( )。[交通银行真题]A.减少政府支出 B.向居民
易发生水解的药物为()A.酚类药物 B.烯醇类药物 C.杂环类药物 D.
下列费用中,属于应在规费清单中列项的有()。A.安全文明施工费 B.工会经费
最新回复
(
0
)