首页
登录
职称英语
I assume the construction of the new airport ______ at the end of last year.A、mu
I assume the construction of the new airport ______ at the end of last year.A、mu
游客
2023-07-21
35
管理
问题
I assume the construction of the new airport ______ at the end of last year.
选项
A、must complete
B、must be completed
C、must have been completed
D、must have completed
答案
C
解析
我想新机场的建设肯定是去年年底完成的。本题考查情态动词must表示推测的用法,意为“肯定,必定,非常可能”,根据时间标志at the end of last year,本题中must是对过去的情况的推测,后跟have done;又因 complete与construction构成动宾关系,故用被动形式have been done。
转载请注明原文地址:https://tihaiku.com/zcyy/2856015.html
相关试题推荐
[originaltext]Oneoftheimportantmaterialsusedintheconstructionofbu
Wehaveto_____________(与其他公司竞争)forthecontractfortheconstructionofthebr
A、BecauseitisthelargestairportinAmerica.B、Becauseithasagoodsorting
[originaltext]W:Airsecuritychecksintheairportalwaysmakemenervous.I’m
Iassumetheconstructionofthenewairport______attheendoflastyear.A、mu
Webeganto______thebricksfromthetruckandcarrythemtotheconstruction
Inatyphoon,winds______aspeedgreaterthan120kilometersperhour.A、assume
Theairplane______bythetimeIarriveatPudongInternationalairport.A、hast
IwassolatearrivingattheairportthatI______hadtimetoboardtheplane.A
Atlastsheleftherhouseandgottotheairport,______(结果却看到飞机正在飞走).onlytose
随机试题
Fewpeopleexpectluxurywhileflying,butthesedays,eventhebasicsseem
A—TajMahalB—HangingGardensofBabylonC—theG
金属辐射板采用蒸汽做热媒时的蒸汽压力要求为()。A.≥400kPa、≮200
梯形断面水渠按均勻流设计,已知过水断面A=5.04m2,湿周x=6.73m
患儿,2岁。发热1天,壮热口渴,烦躁哭闹,疹色鲜红,疹点稠密,小便短赤,大便秘结
A.13 B.28 C.33 D.49
选项的四个图形中,只有一个是由题干四个图形拼合(只能通过上、下、左、右平移),请
从开放登记国的角度看,开放登记的目的在于( )。A.改善国际收支 B.维持和
以下是某求助者做MMPI的测验结果。 从临床量表得分来看,可以判断该求
纳税人停业期满不能及时恢复生产、经营的,应当在()向税务机关提出延长停业登记。A
最新回复
(
0
)