问题 沥青贯入碎石基层施工步骤包括:①撒布主层集料;②压路机碾压;③浇洒沥青;④撒布嵌缝料;⑤撒布封层料。正确的施工顺序是(   )。A.①→②→③→④→②→③→④→②→③→⑤→② B.①→③→④→②→③→④→②→③→⑤→② C.①→②→④→②→③→④→②→③→⑤→②→③ D.①→③→②→④→②→③→④→②→③→⑤→②→③

选项 A.①→②→③→④→②→③→④→②→③→⑤→②
B.①→③→④→②→③→④→②→③→⑤→②
C.①→②→④→②→③→④→②→③→⑤→②→③
D.①→③→②→④→②→③→④→②→③→⑤→②→③

答案 A

解析 2022版教材P60
本题考查的是路面沥青稳定基层施工。沥青贯入碎石基层施工顺序:撒布主层集料→压路机碾压→浇洒沥青→撒布嵌缝料→撒布封层料→最后碾压。