When required the perform Integrated Cha

免费题库2022-08-02  38

问题 When required the perform Integrated Change Control Process includes (  ),whichis a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for conveying and communicating such decisionsA.BBCB.CCBC.BCBD.CBC

选项 A.BBC
B.CCB
C.BCB
D.CBC

答案 B

解析 当需要时,执行综合变更控制过程包括变更控制委员会(CCB),这是一个正式的特许团体,负责审查批准推迟或拒绝对项目的变更,并负责传达这些决定。
转载请注明原文地址:https://tihaiku.com/congyezige/2412427.html

最新回复(0)