When required the perform Integrated Change Control Process includes ( ),whichis a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for conveying and communicating such decisionsA.BBCB.CCBC.BCBD.CBC
选项
A.BBC
B.CCB
C.BCB
D.CBC
答案
B
解析
当需要时,执行综合变更控制过程包括变更控制委员会(CCB),这是一个正式的特许团体,负责审查批准推迟或拒绝对项目的变更,并负责传达这些决定。
转载请注明原文地址:https://tihaiku.com/congyezige/2412427.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
Teamsarerequiredformostengineering
Teamsarerequiredformostengineering
Teamsarerequiredformostengineering
Teamsarerequiredformostengineering
Teamsarerequiredformostengineering
Teamsarerequiredformostengineering
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
随机试题
Foryearsmenandwomenhavebeengettingmarried.Theysaytheirwedding【B1
[originaltext]W:Isthelibraryopeneveryday?M:Exceptonweekends.Itisope
某工程项目建设期为3年,建设期内每年初贷款500万元,年利率为10%,运营期前3
四川真题:我国现行高等学校内部管理体制是()。A.党委领导下的校长负责制 B
循行于下肢外侧中线的是:A.足阳明胃经 B.足太阴脾经 C.足少阳胆经 D
患者男性,38岁,撞车后被方向盘挤压上腹部4小时,上腹部剧烈疼痛,向右肩及腰部放
共用题干 Parkinson'sDisease1Parkinson'sd
下列关于职工因工致残待遇的描述正确的有()A:职工因工致残被鉴定为一级至四级伤残
共用题干 某建设单位建设一热电厂。该单位委托甲工程监理公司对工程进行监理,委托
投标建设工程一切险的工程,保险人对()造成的损失不予赔偿。A.地面下陷 B
最新回复
(
0
)