问题 is primarily concerned with defining and controlling what is and is not included in the project.A.Project Time ManagementB.Project Cost ManagementC.Project Scope ManagementD.Project Communications Management

选项 A.Project Time Management
B.Project Cost Management
C.Project Scope Management
D.Project Communications Management

答案 C

解析 项目范围管理是项目管理(包括时间、成本、沟通)的基础。
项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。
选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理。因此应选择C。